fbpx

Stadium renovations coming soon to Mill Valley, De Soto high schools

Share this story:

Athletics facilities at both Mill Valley and De Soto high schools will be renovated in the coming months, and district staff gave the school board a status update on the projects last month.

The renovations are part of a series of projects funded from an $85 million bond issue approved by voters in May 2018. Here’s where the two projects stand:

Mill Valley High

The stadium at Mill Valley High will undergo some renovations that the district expects to complete in summer 2020. These include additional bleacher seating and storage, as well as a new press box, track resurfacing and installing artificial turf at the soccer field. Leading the project design is HTK Architects. Total cost is $3.4 million.

Some specifics:

  • 1,392 new seats + 2,034 existing on home side = 3,426 total seating
  • 533 new seats + 533 existing on visitor side = 1,066 total seating
  • Remove portable bleachers on visitors side
  • Replace 288 square foot press box with a new 800 square foot press box

Scott Hazelitt with the design consultant HTK Architects said on Feb. 3 that one issue remains with the Mill Valley stadium light poles: Once the additional bleachers are installed on the home side, the light poles will partially block view of the field for those seated behind them.

District staff and architects are looking into an alternative that would move the light poles outside of the seating area, which means the lights must be higher and brighter. Alvie Cater, district spokesperson, said the design team is planning to complete a light study and find ways to utilize LED technology and control light spillage outside of the stadium.

The project will be bid with both options for the light poles, and neither of these plans are expected to delay the project, Cater added.

Concerning the new press box, Hazelitt said they will bid the project with multiple proposals for construction materials, one of which includes the use of shipping containers. Shipping containers instead of more traditional materials could result in about $350,000 in cost savings, according to an estimate from HTK Architects.

Never miss a story
about your community
See for yourself why more than 50,000 Johnson Countians signed up for our newsletter.
Get our latest headlines delivered for FREE to your inbox each weekday.

The Shawnee planning commission will review final plans for Mill Valley High in March, after which the project will go out for bid.

De Soto High

The stadium at De Soto High is also slated for renovations this year; upgrades are part of the district’s master site plan that the school board approved in November. Improvements this year include additional bleacher seating and parking, building new locker rooms and concession areas, and installing artificial turf for the soccer field.

Some reconfiguration of the site has delayed the start date for most of the project from this summer to November.

Steve Deghand, director of facilities, said the new plans call for relocating the new locker room area from a stand-alone building on the site to a location underneath the bleachers. The new location places the locker rooms between the football and soccer fields.

The design changes prevent upgrades from being completed simultaneously for the soccer field turf and the locker room area, Deghand said, because it would impact practices and games during the soccer and football season.

“Bottom line is, we can’t do all of that in a three-month span, starting after Memorial Day and finishing by August,” Deghand said.

Completion is now expected to be in August 2021.

De Soto High will also have additional parking near the athletics facilities and an access road to the new parking area from 87th Street. That part of the project $1.6 million will begin this summer. The rest of the project is in the design phase, so costs are not finalized, Cater noted.

About the author

Leah Wankum
Leah Wankum

Hi there! I’m Leah Wankum, and I’m the Post’s Deputy Editor. I’m thrilled to call Johnson County home, and I’m deeply committed to the Post’s philosophy that an informed community is a strong community.

I’m a native of mid-Missouri, and attended high school in Jefferson City before going on to the University of Central Missouri, where I earned a master’s degree in mass communication.

Prior to joining the Post as a reporter in 2018, I was the editor of the Richmond News in Ray County, Missouri. I’ve also written for several publications, including the Sedalia Democrat and KC Magazine.

Have a story idea or a comment about our coverage you’d like to share? Email me at leah@johnsoncountypost.com.