Demolition of old Kmart in Merriam set to start in October

Share this story:

The old Kmart along Shawnee Mission Parkway in Merriam, which has stood empty for nearly a decade, will finally be torn down in the coming weeks, paving the way for a new $130 million mixed-use development on the site at Shawnee Mission Parkway and Antioch Road.

Driving the news: Matt Pennington, president of Drake Development, told the Post via email that asbestos remediation will begin at the site later this month.

  • Demolition of the former Kmart building is expected to begin in early October, Pennington said.
  • This aligns with the timeline developers already laid out in city documents stating demolition and sitework will begin on or before Dec. 31, 2022.

Why it matters: This is the first time in almost a decade that there will be work at the old Kmart, which closed in January 2013.

Background: After working with developers for more than a year on a potential project, Merriam City Council approved a $130 million redevelopment of the former Kmart site in July dubbed Merriam Grand Station.

Zooming out: The Merriam Grand Station plan promises to remake the prominent 12-acre tract that sits just off Interstate 35.

  • The plan includes building three restaurants, a large public plaza, a parking structure and two apartment buildings totaling at least 350 total units.
  • Two restaurants nearby, a Freddy’s and Krispy Kreme, will remain after the new development.
  • The future of a third restaurant, a Pegah’s Family Restaurant on the northeast corner of the property, is less clear.
  • The restaurant announced a temporary closure to begin on Oct. 2 and said they would be back next year with a “brand new building” but Pennington says the Pegah’s is not part of the new Merriam Grand Station redevelopment.
Kmart Merriam
The Kmart building has stood vacant since the store closed in 2013. File photo.

What’s next for Merriam Kmart site:

Commercial and residential portions of the project are expected to be “pad ready” on or before Dec. 31, 2023.

  • According to the agreement with the city, the infrastructure needs to be finished by 2024, with the three restaurants outlined in the project completed and operational by June 30, 2025.
  • In its entirety, Merriam Grand Station needs to be completed by Dec. 31, 2026, according to the development agreement.

About the author

Juliana Garcia
Juliana Garcia

👋 Hi! I’m Juliana Garcia, and I cover Prairie Village and northeast Johnson County for the Johnson County Post.

I grew up in Roeland Park and graduated from Shawnee Mission North before going on to the University of Kansas, where I wrote for the University Daily Kansan and earned my bachelor’s degree in  journalism. Prior to joining the Post in 2019, I worked as an intern at the Kansas City Business Journal.

LATEST HEADLINES