Roeland Park sells land to developer, setting up $50M+ apartment, retail project

Editor’s note: The original version of this story contained an error about the price per square foot of the land sale relative to the price assigned to the land in a previous, unsuccessful development proposal. The land was valued the same in both instances. It was not valued higher in this instance than with the previous proposal.

The Roeland Park City Council took another step this week toward a proposed $50-$75 million development for The Rocks site at 4800 W. Roe Blvd., where the city pool was located a few decades ago.

City sells land for $3.45 million: The council unanimously approved an agreement to sell about 6.6 acres of land to the developer, EPC Real Estate Group LLC of Overland Park, for $3.45 million, or $12 a square foot.

Project details for The Rocks site in Roeland Park

The Rocks site for sale sign in Roeland Park
Roeland Park will sell the land for about $3.45 million, or $12 a square foot.

In late August, Austin Bradley, EPC’s executive vice president, updated the council on the company’s progress since the council approved entering a 90-day memorandum of understanding in July. Project plans call for the following components, according to Bradley’s presentation:

  • About 280 apartments
  • A two-story restaurant of up to 5,000 square feet, possibly with a rooftop patio
  • Retail and commercial space
  • A parking garage for the project’s residents that will be minimally visible
  • A private-public plaza, which will be “really more of a beer garden environment,” according to Bradley
  • Fitness facilities and other amenities

Project cost and timeline: The estimated project cost is now “trending towards the upper end” of the $50 million to $75 million range, Bradley said.

  • The company hopes to start construction at The Rocks site in mid-2023 and finish the project about 20 months later.
  • According to the land purchase agreement, Roeland Park can continue to use the site’s Public Works facility through Oct. 1, 2023. The agreement allows EPC a 90-day due diligence period by which the company must receive various approvals from the council, including for a development agreement
  • Roeland Park has been actively seeking development agreements for The Rocks site since 2017.

What kind of apartments will be included? Bradley told the Shawnee Mission Post in late August that it was still too early in the process for him to have details on the ranges of apartment rents or sizes.

Jerry LaMartina is a freelance journalist who contributes frequently to the Shawnee Mission Post and other Kansas City-area publications. He can be reached at lamartina.jerry@gmail.com.

About the author

Jerry LaMartina
Jerry LaMartina

Jerry LaMartina is a freelance journalist who contributes to the Johnson County Post and other Kansas City-area publications. He can be reached at lamartina.jerry@gmail.com.

LATEST HEADLINES