Here’s a timeline for U.S. 69 toll lane project in Overland Park

Share this story:

Work on the highly anticipated U.S. 69 toll lane project through Overland Park is expected to come in different phases over the next several years, according to the Kansas Department of Transportation.

Construction officially began earlier this year on the project, which will add toll lanes going both directions on U.S. 69 between 103rd and 151st streets.

Most of construction on the U.S. 69 toll lanes is expected to take place in 2024.

Below is a look at the latest timeline provided by the Kansas Department of Transportation for when residents can expect different elements to be under construction for the multi-year project.

*Project representatives gave no specifics about when express toll lanes themselves will be built, except to note that all toll lane work is slated to be completed by the end of 2025.

First things first: Blue Valley Parkway and 135th this year

  • Blue Valley Parkway at U.S. 69 interchange: Prep work for ramp construction (which is set for 2024) — spring 2023. No specific closures announced yet.
  • West 135th Street at U.S. 69 interchange: Relocating utilities, other prep work — summer 2023. No specific closures announced yet.

Long-term closures planned at 119th and 143rd next year

  • U.S. 69 bridges over West 135th Street: Full replacement — spring into fall 2024. Phasing with separate closures to maintain traffic flow. No specific closures announced yet.
  • U.S. 69 bridges over West 143rd Street: Widening to add new toll lanes — spring into fall 2024. Phasing as well as a 90-day closure planned.
  • West 119th Street under U.S. 69 bridges: Reconstruction with new on/off ramps, remodeling of bridges — summer into fall 2024. A 60-day closure of 119th planned.
  • Blue Valley Parkway at U.S. 69 interchange: New ramps and reconstruction — summer 2024. No specific closures announced yet.
Toll lane construction
State and city officials held an official groundbreaking ceremony in February for the 69Express project. File photo.

Final work expected in 2025-2026

  • U.S. 69 bridges over Interstate 435: Full replacement, adding toll lanes from I-435 to West 103rd Street. No specific closures announced yet.
  • West 167th Street at U.S. 69: Adding southbound ramps and roundabouts, expanding 167th to four lanes. No specific closures announced yet.
  • Noise walls: By the end of 2026, crews will finish building 11 noise walls along U.S. 69 from 119th to 151st.

Go deeper: Overland Park officially breaks ground on U.S. 69 toll lanes

About the author

Nikki Lansford
Nikki Lansford

Hi! I’m Nikki, and I cover the city of Overland Park.

I grew up in southern Overland Park and graduated from Olathe East before going on to earn a degree in journalism from the University of Missouri. At Mizzou, I worked as a reporter and editor at the Columbia Missourian. Prior to joining the Post, I had also done work for the Northeast News, PolitiFact Missouri and Kaiser Health News.

We work hard to make it easy for you to keep up on your community with short, to-the-point coverage and easy-to-scan newsletters — but we can’t produce local coverage without local support. To our nearly 7,000 subscribers: THANK YOU! If you aren’t a subscriber yet, we hope you’ll give one a try today — your first month of full access is just $1!

LATEST HEADLINES