Prairie Village plans full 83rd Street rehab project in 2027 — What’s changing?

Improvements to 83rd Street near Corinth Quarter in Prairie Village include a pedestrian island and modified lanes.

Shoppers and drivers at Prairie Village’s Corinth Quarter and Corinth Square shopping centers will notice changes to 83rd Street next year.

The Prairie Village City Council on July 20 unanimously approved a rehabilitation plan for 83rd Street between Mission Road and Somerset Drive, which runs in between Corinth Quarter and Corinth Square.

While Village Vision 2.0, the city’s comprehensive plan, contemplated on-street parking and consolidation of entrances, Public Works Director Keith Bredehoeft said at the meeting, a group of councilmembers and business representatives landed on a scaled-back version of that concept.

The city council approved project envisions a pedestrian connection and island about halfway through this section of 83rd Street as well as some modified right-turn lane lengths.

Here’s a look at the changes that are in the works for the “Corinth Corridor” of 83rd Street.

A look at the changes

83rd Street in Prairie Village between Mission Road and Somerset Drive. Photo credit Juliana Garcia.
83rd Street in Prairie Village between Mission Road and Somerset Drive. Photo credit Juliana Garcia.

Drivers and pedestrians alike will notice differences once the project, slated for 2027 under the city’s County Assistance Road Systems, or CARS, program, is completed.

Bredehoeft said that after discussing various ideas for this specific corridor, the group of councilmembers and business representatives landed opted against any on-street parking for 83rd Street between Mission Road and Somerset Drive.

There are also no plans to change the access points into either Corinth Square or Corinth Quarter off of 83rd Street.

The most noticeable change will be the pedestrian crosswalk, accompanied by a pedestrian island, about midway through this stretch of 83rd Street.

Along this “Corinth Corridor,” there will also be some curb extensions to make some portions of the roadway narrower.

This includes additional curbing near the pedestrian crosswalk, which intends to make the width of the roadway pedestrians need to cross shorter.

A presentation of the specific changes is embedded in the document below:

Loader Loading...
EAD Logo Taking too long?

Reload Reload document
| Open Open in new tab

These upgrades will cost an additional $75K

Bredehoeft told the city council last week that the standard CARS project for this stretch of the road is an estimated $350,000.

A standard CARS project includes concrete work and asphalt upgrades, Bredehoeft said.

The curb pedestrian island work and the grading for some new green space is an additional $75,000, Bredehoeft said.

“We kind of feel this is the kind of stuff we would do a lot of with the normal project anyway, if we look at opportunities to make things better when we get done with our projects,” Bredehoeft said.

Bredehoeft said the city will also look at enhanced landscaping, pedestrian lighting and other lighting along the north side of the street.

Keep reading traffic and roads news: More than a year after a car hit 2 kids, Fairway extends school zone near St. Agnes

About the author

Juliana Garcia
Juliana Garcia

? Hi! I’m Juliana Garcia, and I cover Prairie Village and northeast Johnson County for the Johnson County Post.

I grew up in Roeland Park and graduated from Shawnee Mission North before going on to the University of Kansas, where I wrote for the University Daily Kansan and earned my bachelor’s degree in  journalism. Prior to joining the Post in 2019, I worked as an intern at the Kansas City Business Journal.

Have a story idea or a comment about our coverage you’d like to share? Email me at [email protected].

LATEST HEADLINES